Through years of experience and know-how,
we create customer satisfaction with perfect service.
A.I.F. provides the optimal solution by analyzing the characteristics of the cargo requested by the customer based
on years of project cargo transportation experience and know-how.
The A.I.F. project teams collectively control and manage all procedures from
the primary design stage to the end of the entire process through thorough preemptive transportation planning, analysis, and establishment of dedicated organizational systems.
Europe
-
1Propeller Project
Propeller Project
- PERIOD : 28.Jul.2022
- ITEM : Propeller
- POL : Hamburg, Germany
- POD : Busan, Korea
Key Performance
Port Handling / Breakbulk loading onto container vessel
-
2Bio Friends Project
Bio Friends Project
- PERIOD : 11.May.2022
- ITEM : Breakbulk
- POL : Hamburg, Germany
- POD : Busan, Korea
Key Performance
Port Handling / Breakbulk loading onto container vessel
-
3Renault MCA Project
Renault MCA Project
- PERIOD : 03.Jul.2020
- ITEM : Renault MCA 2400
- POL : Dangjin, Korea
- POD : Renault MCA, France
Key Performance
Onshore Onshore Antwerp D/port handling Interim storage at d/port H/Ls barge transport from d/port to Ghlin, Belgium Unloading at barge d/port by hiring 2 units of 500MT crane H/Ls inland transport from barge d/port to Renault site
-
4Hanwha Total Solution Project
Hanwha Total Solution Project
- PERIOD : 14.Feb.2020
- ITEM : Hanwha Total Solution Revamping
- POL : Marghera, Italy
- POD : Pyeongtaek, Korea
Key Performance
H/Ls chartering
-
5Energinet. DK Transformer Transport
Energinet. DK Transformer Transport
- PERIOD : Oct.2012
- ITEM : Reactor
- POL : Busan, Korea via Rotterdam, Netherlands
- POD : Denmark Aabenraa, Kossoe
Key Performance
Transportation of Reactor for ENERGINET. DK (7.80m(L) x 4.20m(W) x 5.20m(H) / 1 unit / 150.00 M/Ton)
-
6Doosan Heavy Industry Water and Electricity Infrastructure Project
Doosan Heavy Industry Water and Electricity Infrastructure Project
- PERIOD : 2008~2009
- ITEM : Gas Turbines and Generators
- POL : Germany
- POD : the U.A.E Jebel Ali Job
Key Performance
Transportation of Gas Turbines and Generators from Siemens Germany and Other Sub Suppliers to the U.A.E Jebel Ali Job Site
-
7SK Energy Heat Exchanger Machine Export
SK Energy Heat Exchanger Machine Export
- PERIOD : 18.Sep.2009
- ITEM : Transportation of Heat Exchanger Machine
- POL : Arrle, France
- POD : Busan, Korea
Key Performance
Transportation of Heat Exchanger Machine for the SK energy
-
8Dongbu Steel HR Project
Dongbu Steel HR Project
- PERIOD : Aug.2008~Apr.2009
- ITEM : Major Facilities for the Electricity Plant
- POL : Danieli, Tenova, Marghera, Italy
- POD : Busan, Korea
Key Performance
Transportation of Major Facilities for the Electricity Plant
-
9Amman East Power Project
Amman East Power Project
- PERIOD : Jul.2007~Apr.2009
- ITEM : Major Power Plant Materials
- POL : Italy
- POD : Aqaba, Jordan
Key Performance
Transportation of Major Power Plant Materials From Suppliers in Italy
-
10SK New FCC Project
SK New FCC Project
- PERIOD : 2007~2008
- ITEM : FCC (Fluid Catalytic Cracking) Equipment
- POL : Oberhausen, Germany & Marghera, Italy
- POD : Busan, Korea
Key Performance
Transportation of FCC (Fluid Catalytic Cracking) Equipment Used in the Gasfication Desulphurization Process That Inproves Refined Oil Production